Two supergrid transformers had reached Creag Dhubh in Argyll by the time SSE reported on 18 November. At Crossaig North, the first of a pair had arrived. Across its wider Pathway to 2030 programme, SSEN Transmission had secured 27 of 34 major consents. These are three different milestones. A transformer can reach a substation before the lines and equipment around it are ready to carry power.
The sequence creates a difficult purchasing decision. Wait for the last permission and the manufacturer may already have promised the next slot to somebody else. Reserve the slot early and a change in planning or technical specification could leave customers carrying a cost for equipment that cannot go where it was intended.
SSE described a move towards buying across a portfolio of projects in an April briefing. Ofgem’s March 2025 advance procurement decision also gives British transmission owners a route to secure supply-chain capacity earlier. Neither document establishes the contract terms for the transformers delivered in Argyll.
What a board buys when it books early
Through the Financial Stewardship part of WCRC Leadership Equity Research, the useful comparison is between two supplier offers. What is the earliest delivery date available after consent? What deposit buys an earlier slot today, and how much of it is recoverable? A project team that expects a year's delay should be able to point to the supplier schedule behind that estimate.
What a reservation actually protects
A manufacturing slot has value only for a project that can use the time saved. Suppose a transformer ordered after planning approval would arrive six months later than one reserved today. If the associated line would still be under construction for those same six months, early delivery alone brings the first electricity connection forward by zero days. Someone must nevertheless take delivery, store the equipment and decide who is responsible for its condition. This is an illustrative sequence. SSE has not published that timetable for either Argyll site.
Now change one assumption. If a completed substation would otherwise stand idle waiting for its transformer, losing the manufacturing slot could delay the whole connection. In that case the procurement team can put a date against the benefit of early commitment. The finance team can ask which payments are refundable at each stage, including after the factory has ordered materials or started work. A small reservation payment and a binding commitment to buy the finished unit expose the project to different losses.
There is also information in the 27 consents figure that a percentage would hide. Seven major consents remained across the programme at the reporting date. That does not identify which of the seven, if any, sat on the critical path for a particular delivery. Dividing 27 by 34 gives a measure of administrative progress. It gives no probability that an individual substation will be ready on time.
For households funding the network, the test of the procurement decision will come at commissioning. Record the earliest credible connection date under each purchasing option when the order is placed. Compare that forecast with the connection eventually achieved, including the causes of any slippage. Otherwise an on-time equipment delivery can be counted as a success even when it saved the customer no time at all.
A portfolio can change the answer. A second substation that needs compatible equipment could take the slot if the first scheme slips. That option has value only if the engineering requirements, transport arrangements and contract allow the switch. The question for a board paper is precise enough to put to a procurement director: which other project could use this reservation, and who has checked?